Santa Ana Gardens Bikeway Extension Project

Santa Ana Gardens Bikeway

Background

The Santa Ana Gardens Channel Bikeway Extension Project will improve safety for bicyclists and pedestrians and will provide connections to the existing and future bikeways.  It is not only a bikeway – this will be a new path that provides a connection to the community, providing a safe walkway to nearby schools, Jerome Park, Friendship Park and adjacent neighborhoods.

Phase 1 of the Santa Ana Gardens Bikeway was completed in 2016 and is located immediately east of Jerome Park and Monte Vista Elementary School, between Monta Vista Avenue and McFadden Avenue.

    Project Scope

    Crews will transform a dirt County access road (next to the Santa Ana Gardens Flood Control Channel) into a paved path for public use — for bicyclists and pedestrians. This new path will provide a connection to the community by providing a safe bikeway and walkway to nearby schools, Jerome Park, Friendship Park and adjacent neighborhoods.

    Construction activities will include:

    • Dedicated path off the roadway for bicyclist and pedestrians (short portion of bikeway at Myrtle Street will be on the roadway)
    • Cable-railing fencing
    • 8-feet tall, high-durability fencing
    • Curb ramp reconstruction
    • Friendship Park renovation
    • Landscaping
    • Security lighting
    • Crosswalk at Willits Street

    Location

    From the southern end at Monta Vista Avenue to the northern end at 1st Street, located midway between Sullivan Street and Daisy Avenue.

    Status

    In Construction

    Anticipated Construction Duration 
    November 28, 2022 — Fall 2023

    Work Days/Hours
    Monday — Friday, 7 a.m. — 4:00  p.m.* 

    *Note: Start time along Monte Vista Avenue and adjacent to homes will be adjusted to minimize impacts. 

    The construction schedule is subject to change.


    Updates

    December 2022
    Monte Vista Avenue Road Closure Delay / Rescheduled to 12.29.22 (English 12.22)

    October 2022

    Construction Alert (English 10.22 | Spanish 10.22)


    Project Contact

    Jeaniene Casiello, OC Construction
    (714) 245-4500
    Contact Form