Laguna Canyon Channel Replacement Project

Fly over the project in construction with our OC Survey team. March 2023.

The Laguna Canyon Channel Replacement Project began in September  2022 and will continue through May 2023. Construction hours are Monday through Friday from 7:30 a.m. to 6 p.m. Construction will involve the use of large equipment to remove and replace the channel and reconfigure the pedestrian crossings or bridges that cross over the channel, replace landscaping and hardscaping (in coordination with the City of Laguna Beach), and remove trees that may pose a risk to the channel.

Approximately two-thirds of the parking spaces along Laguna Canyon Frontage Road will be open for adjacent businesses during each phase of construction, while a portion of parking spaces will be temporarily closed to accommodate this work and equipment.

The sidewalk along Laguna Canyon Road near the project area will be closed during construction, a temporary pedestrian walkway with protective barrier will be available. To accommodate the temporary pedestrian walkway, the parking along Laguna Canyon Road adjacent to the sidewalk within the construction area will be closed for the duration of construction.

Background

Laguna Canyon Channel Replacement Project | 2019 Storm Channel Wall Failure

During heavy storms in February 2019, approximately 265 feet of the channel wall closest to Laguna Canyon Road collapsed. An investigation determined that an emergency repair was needed to maintain flood protection to the community. In March 2019, a temporary repair was implemented to fix the collapsed wall and bracing was added to prevent additional failures. The project will replace the temporary repairs with a permanent solution for the channel.

 

Project Scope

The Laguna Canyon Channel Replacement Project, between Laguna Canyon Frontage Road and Woodland Drive, consists of removing and replacing the rectangular concrete channel, reconfiguring small concrete pedestrian crossings, removing and replacing softscape and hardscape that may be damaged or removed in order to construct the Project, and removing trees within the Project limits that pose a risk to the channel.

 

Location

Click on image below to download PDF.

Laguna Canyon Channel Replacement Project Map

 

Status

Construction


Project Contact

Teddy Kamarzarian
phone (714) 955-0315  
emailProjectInfo@ocpw.ocgov.com


Construction Notifications

picture_as_pdf April 2023

picture_as_pdf March 2023

picture_as_pdf January 2023

picture_as_pdf September 2022


Meetings

Orange County Board of Supervisors (Approve Agreement with City of Laguna Beach and Caltrans)

Tue. August 23, at 9:30 a.m.

picture_as_pdf Agenda 08.23.22
smart_displayBoard Meeting Recording 08.23.22


City of Laguna Beach City Council Meeting (Approve Agreement with Orange County Flood Control District and Caltrans)

Tue. August 2, at 6 p.m.

picture_as_pdf Recap 08 .02.22
smart_display City of Laguna Beach Live Stream Recording 08.02.22


Orange County Board of Supervisors (Award the Construction Phase Services Contract)

Tue. June 7, at 9:30 a.m.

picture_as_pdfAgenda 06.07.22
smart_display Board Meeting Recording 06.07.22


City of Laguna Beach Planning Commission (Design Review 22-0735 and Coastal Development Permit 22-0736)

Wed., May 18, 2022 at 6 p.m.

picture_as_pdfAgenda /Documents 05.18.22
smart_display Recap 05.18.22
smart_display City of Laguna Beach Live Stream Recording 05.18.22


City of Laguna Beach Planning Commission (OCPW Presentation)

Wed., August 4, 2021 at 6 p.m.
picture_as_pdf Event Flyer 08.04.21
smart_display Recap
smart_display City of Laguna Beach Live Stream Recording 08.04.21


Orange County Board of Supervisors (Award Design Phase Services Contract)

Tue., March 23, 2021 at 9:30 a.m.

picture_as_pdfMinutes 03.23.21
smart_display Board Meeting Recording 03.23.21


Social

Facebook
Twitter
Instagram